01-0248R

RESOLUTION AWARDING CONTRACT TO FOUR STAR CONSTRUCTION, INC., FOR BAYFRONT FESTIVAL PARK/PHASE III - TOILET BUILDING, IN THE AMOUNT OF $139,409.

BY PRESIDENT EDWARDS:

        RESOLVED, that Four Star Construction, Inc., be and hereby is awarded a contract for the construction of the Bayfront festival park/Phase III - toilet building for the city architect division in accordance with specifications on its low specification bid of $139,409, terms net 30, FOB job site, payable out of Capital Improvements Fund 0450, Dept./Agency 015, Organization 1999, Object C921.



STATEMENT OF PURPOSE: This resolution will authorize the construction of Bayfront Festival Park/Phase III by Four Star Construction, Inc. for $139,409 to be paid from Capital Improvement Fund 0450. Phase III is for the public toilet building immediately adjacent to playfront. This project will be built in conjunction with the Bayfront Park/Phase II improvements and is scheduled to be substantially completed by August 4, 2001. Four Star Construction was the lowest of the four above companies who responded. The estimated cost of this project is $150,000. The uncommitted funds in Object C921 is $3,173,548. Bid No. 01-0356; Job No. OT -9636d
 
Tabulation of bids received March 16, 2001
Four Star Construction, Superior, WI $139,409
Amendola Construction Company, Duluth, MN $142,500
Erling Hansen Contractor, Duluth, MN  $147,000
Don Holm Construction, Duluth, MN $150,000