01-0270R

RESOLUTION AMENDING RESOLUTION 98-0889 AWARDING CONTRACT TO STOUT MECHANICAL, INC., FOR INSTALLING A HIGH PRESSURE STEAM LINE CONDUIT SYSTEM TO THE LAKE SUPERIOR CENTER, TO INCREASE THE AMOUNT BY $30,866.29 FOR A NEW TOTAL OF $117,194.29.

BY COUNCILOR ECKENBERG:

        RESOLVED, that Resolution 98-0889 to Stout Mechanical, Inc., for installation of a high pressure steam line conduit system to the new Lake Superior center, be amended to increase the amount by $30,866.29 for a new total of $117,194.29, payable out of Steam District #1 Fund 0540, Dept./Agency 920, Organization 1490, Object 5980.



STATEMENT OF PURPOSE: This resolution will authorize an amendment to Resolution 98-0889, passed on September 28, 1998 for installation of high pressure steam line conduit system to the new Lake Superior Center. This increase was for additional installation of six inch expansion joint, removal of extra concrete debris and other required changes to the project. The estimated budget of this project is $181,500. Bid No. 98-0873
 
Tabulation of bids received September 17, 1998
Stout Mechanical, Duluth, MN $  86,328
A.W. Kuettel and Sons, Duluth, MN $  95,151
Stack Brothers, Superior, WI $103,400