01-0390R

RESOLUTION AWARDING CONTRACT TO NORTHLAND CONSTRUCTORS, LLC, FOR CONSTRUCTION OF YEAR 2001 STREET IMPROVEMENT PROJECT OF CONGDON PARK CENTRAL IN THE AMOUNT OF $939,337.10.

BY COUNCILOR ECKENBERG:

        RESOLVED, that Northland Constructors, LLC, be and hereby is awarded a contract for construction of the year 2001 street improvement project of Congdon Park Central for the engineering division in accordance with specifications on its low specification bid of $939,337.10, terms net 30, FOB job site, payable out of Street Improvement Project Fund 0440, Dept./Agency 038, Organization 0103, Object 5530.



STATEMENT OF PURPOSE: This resolution will authorize the construction of the year 2001 street improvement project at Congdon Park Central including Ridgewood Road between Fourth Street and 34th Avenue East; 34th Avenue East between Fourth Street and Ridgewood Road; Valley Drive between the center of Section 12 to Oxford Street by Northland Constructors, LLC, for $939,337.10 to be paid from Street Improvement Program Fund 0440. Northland Constructors was the lowest of the five companies who responded. The estimated cost for this project is $1,056,125. The unobligated amount in Object 5530 is $1,083,431.12. Bid No. 01-0467; Job No. 9190RS01
 
Tabulation of bids received May 8, 2001
Northland Constructors, Duluth, MN $ 939,337.10
Wagner Construction, So. International Falls, MN $ 958,777.60
Utility Systems of America, Eveleth, MN $ 995,262.26
Letourneau and Sons, Duluth, MN $1,077,506.00
Levine and Son, Inc., Duluth, MN $1,177,305.10