01-0585R

RESOLUTION AWARDING CONTRACT TO BILLMAN CONSTRUCTION, INC., FOR YEAR 2001 STREET IMPROVEMENT PROJECT AT CENTRAL HILLSIDE-13TH STREET, IN THE AMOUNT OF $216,979.25.

BY COUNCILOR ECKENBERG:

        RESOLVED, that Billman Construction, Inc., be and hereby is awarded a contract for construction of Year 2001 Street Improvement at Central Hillside-13th Street between Central Entrance to 665 feet westerly for the engineering division in accordance with specifications on its low specification bid of $216,979.25, terms net 30, FOB job site, payable out of Street Improvement Program Fund 0440, Dept./Agency 038, Organization 0101, Object 5530.



STATEMENT OF PURPOSE: This resolution will authorize the construction of Year 2001 Street Improvement at Central Hillside-13th Street between Central Entrance to 665 feet westerly (see attached map) by Billman Construction for $216,979.25 to be paid from Street Improvement Program Fund 0440. Billman Construction, Inc. was the lowest of the four above companies who responded. The estimated cost for this project is $250,349.70. Bid No. 01-0591; Job No. 9192RS01
 
Tabulation of bids received August 2, 2001
Billman Construction, Hermantown, MN $216,979.25
Nels Nelson and Sons, Cloquet, MN $262,664.00
Northland Constructors, Duluth, MN $267,682.55
Letourneau and Sons, Duluth, MN $270,864.50