04-0073R

RESOLUTION AMENDING RESOLUTION 03-0706 AWARDING CONTRACT TO PROGRESSIVE CONSULTING ENGINEERS, FOR PROFESSIONAL SERVICES RELATING TO THE DEVELOPMENT OF A WATER RATE MODEL FOR THE STORA ENSO PAPER MILL, TO INCREASE THE AMOUNT BY $2,880 FOR A NEW TOTAL OF $12,650.

BY COUNCILOR STOVER:

RESOLVED, that Resolution 03-0706 to Progressive Consulting Engineers for professional services relating to the development of a water rate model for the Stora Enso paper mill, be amended to increase the amount by $2,880 for a new total of $12,650, payable out of Water Fund 0510, Department/Agency 500, Organization 1915, Object 5310.


STATEMENT OF PURPOSE: This resolution will authorize an amendment to Resolution 03-0706, passed on October 14, 2003, for professional services relating to the development of a water rate model for the Stora Enso paper mill. The increase is for additional 32 hours to complete the project. Requisition No. 03-0409; Contract No. C19381-03