05-0119R


RESOLUTION AMENDING RESOLUTION 03-0416 AWARDING CONTRACT TO LHB ENGINEERS AND ARCHITECTS FOR PROFESSIONAL ENGINEERING SERVICES FOR BRIDGE L8477 OVER MILLER CREEK, TO INCREASE THE AMOUNT BY $71,263 FOR A NEW TOTAL OF $93,532.

BY COUNCILOR STEWART:

     RESOLVED, that Resolution 03-0416 to LHB Engineers and Architects for furnishing professional engineering services for Bridge L8477 over Miller Creek, be amended to increase the amount by $71,263 for a new total of $93,532, payable out of Fund 411, Department/Agency 035, Object 5530, Project PI0102TR.


STATEMENT OF PURPOSE:  This resolution will authorize an amendment to Resolution 03-0416, passed on 6/9/2003 for professional services to include preliminary design, final design and bidding phase for Bridge L8477 over Miller Creek at West Tenth Street. Bid No. 03-0456

 