05-0151R


RESOLUTION AMENDING RESOLUTION 04-0203 AWARDING CONTRACT TO LEVINE AND SON, INC., FOR CONSTRUCTION OF A SANITARY SEWER IN DECKER ROAD AND ANDERSON ROAD AND CONSTRUCTION OF A WATERMAIN IN ANDERSON ROAD, TO INCREASE THE AMOUNT BY $254,310 FOR A NEW TOTAL OF $786,000.50.

BY COUNCILOR STOVER:

     RESOLVED, that Resolution 04-0203 to Levine and Son, Inc., for construction of a sanitary sewer in Decker Road and Anderson Road and a watermain in Anderson Road be amended to increase the amounts as follows:

           Increase attributable to sewer construction portion is $22,698, payable out of Special Assessment Fund 0410, Department/Agency 038, Object 5530, Project No. 0195SN;

           Increase attributable to the watermain portion is $231,613, payable out of Water Construction Bond Fund 0511, Department/Agency 500, Object 5532.


STATEMENT OF PURPOSE:  This resolution will authorize an amendment to Resolution 04-0203 passed on 22 March 2004 for construction of sanitary sewer and watermain in Anderson Road and Decker Road. Amendment compensates contractor for differing site conditions causing the directional drilling portion of the work to be changed to a more costly open-cut type construction.

 