05-0573R


RESOLUTION APPROVING SECOND AMENDMENT TO RESOLUTION 03-0650 AWARDING CONTRACT TO LETOURNEAU & SONS, INC., FOR WASTEWATER COLLECTION SYSTEM AND STREET IMPROVEMENTS IN MORGAN PARK-PHASE I, TO INCREASE THE AMOUNT BY $509,892.62 FOR A NEW TOTAL OF $1,992,591.72.

BY COUNCILOR STOVER:

     RESOLVED, that Resolution 03-0650 to Letourneau & Sons, Inc., for the construction of 5,200 feet of sanitary sewer, reconstruct sanitary sewer Pumping Station #20 - Part A and street improvements - Part B in conjunction with the Morgan Park wastewater collection system - Phase I, be amended to increase the amount by $509,892.62 payable out of Sewer Fund 0530, Department/Agency 500, Organization 1905, Object 5533, for a new total of $1,992,591.72.


STATEMENT OF PURPOSE: Resolution 03-0650, Part A (wastewater) and Resolution 04-0204, Part B (street) awarded the work to Letourneau & Sons for $1,482,699.10 to be paid from the Sewer Fund 0430 ($1,087,254.05), the Street Improvement Fund 0440 ($296,584.24) and CDBG Fund 262 ($98,860.81). This resolution will amend Letourneau’s contract by $509,892.62. The extra work orders and increase in quantities are due to poor soil conditions, unknown and unmarked utility obstructions and extremely difficult working conditions in the narrow alleys. The adjusted contract price is $1,992,591.72. A total of $1,597,146.67 to be paid from the Sewer Fund 0530; $296,584.24 to be paid from Street Improvement Fund 0440 and $98,860.81 to be paid from the CDBG Fund 262. Bid No. 03-0539; Job Nos. 0019SN and 0028TR; Contract No. C19526

 

SEE DISCLAIMER