DISCLAIMER

 

05-0612R


RESOLUTION AWARDING CONTRACT TO NORTHLAND CONSTRUCTORS OF DULUTH, LLC, FOR CONSTRUCTION OF HELBERG DRIVE FROM GARFIELD AVENUE TO PORT TERMINAL DRIVE IN THE AMOUNT OF $2,945,496.49.

BY COUNCILOR STOVER:

     RESOLVED, that Northland Constructors of Duluth, LLC, be and hereby is awarded a contract for construction of Helberg Drive from Garfield Avenue to Port Terminal Drive for the engineering division in accordance with specifications on its low specification bid of $2,945,496.49 terms net 30, FOB job site, payable out of Permanent Improvement Program Fund 0411, Department/Agency 035, Object 5530, Project PI0103TR.


STATEMENT OF PURPOSE: The Duluth Seaway Port authority has received federal grant money for the construction of Helberg Drive. Northland Constructors of Duluth was the only respondent to the request for bids. The engineer’s estimate for this project was $5,336,648. The city of Duluth will oversee the construction administration of this project through the delegated contract process and be reimbursed all nonparticipating costs from the Duluth Seaway Port authority. Work is to be paid from PI0103TR Fund 0411, Agency 035, Object 5530. Bid No. 05-0582 PI0103TR


Tabulation of bid received August 22,2005: Northland Constructors, Duluth, MN - $2,945,496.49