06-0496R


RESOLUTION AWARDING CONTRACT TO A.J. SPANJERS COMPANY, INC., FOR THE PHASE III CITY HALL EXTERIOR RESTORATION PROJECT IN THE AMOUNT OF $186,715.

BY COUNCILOR KRAUSE:

     RESOLVED, that A.J. Spanjers Company, Inc., be and hereby is awarded a contract for Phase III City Hall Exterior Renovation in accordance with its combined low bid of $186,715, terms net 30, FOB jobsite, payable out of Capital Improvements Fund 450, Department/Agency 030, Object 5520, Project CP2004-C403, Project CP2005-OT-0501, and Project CP2006-OT-0601.


STATEMENT OF PURPOSE:  This resolution will award a construction contract to A.J. Spanjers Company, Inc., based on its combined low bid of $186,715 and payable out of Capital Improvements Fund. The work would include the replacement of the civic center entry slab to meet Americans with Disabilities Act (ADA)guidelines and protect the police locker room housed beneath this slab. Also included in the work is the re-caulking of all city hall windows and the masonry pointing of select areas in the granite face.


A.J. Spanjers Company, Inc., was the lowest of two bids received. The estimated cost of this project was $180,000.


Bid No. 06-0421

Job No. OT-0601

Tabulation of bids June 6, 2006

A. J. Spanjers Company, Inc., Brooklyn Park, MN

$186,715 

Hovland, Inc., Hermantown, MN

$208,600