07-0558R


RESOLUTION AMENDING RESOLUTION NO. 06-0727 AUTHORIZING A CONTRACT WITH APEX MECHANICAL PLUMBING, HEATING AND UTILITIES FOR INSTALLATION OF A HIGH-PRESSURE STEAMLINE EXTENSION TO FIRST LUTHERAN CHURCH, TO INCREASE CONTRACT #20272 AMOUNT BY $20,838.08, FOR A NEW TOTAL OF $92,938.08.

BY COUNCILOR JOHNSON:

     RESOLVED, that Resolution No. 06-0727 be amended and Contract No. 20272 with Apex Mechanical Plumbing, Heating and Utilities be increased by $20,838.08, for a new total of $92,938.08, payable from the Steam Fund 520, Department/Agency 920, Organization 1499, Object 5530. The increase provides for additional work required in the installation of a high-pressure steamline extension to First Lutheran Church.


STATEMENT OF PURPOSE:  This resolution amends the previous Resolution No. 06-0727 and increases the city’s contract with Apex Mechanical Heating, Plumbing and Utilities by $20,838,08, for a new total of $92,938.08.


This is Change Order #1 for Contract #20272. The increase provides for additional work required in the installation of a high-pressure steam piping system to First Lutheran Church.


The city advertised the original project in September 2006, opened bids on October 5, 2006, and awarded Apex with a contract of $72,100.


Requisition No. 06-0360